Grant Road Improvement Project

City of Tucson's Grant Road Improvement Project

Current Phase - 3 & 4

Current Phase 3 & 4 Information (Sparkman to Swan)

 

Phase 3 & 4 Schedule:​

 

Key Project Features:

  • Widen roadway to 6 lanes
  • Landscaped median islands
  • 5-ft bike lanes w/ 2 ft buffer
  • 5-8 ft wide sidewalks each side of Grant
  • Landscaping & public art
  • Indirect left turns at Alvernon Way
  • Protected bike/pedestrian street crossings
  • Bus pullouts, shelters & benches
  • Drainage features & catch basins

 

GRANT ROAD CONSTRUCTION OVERVIEW

New Tucson Electric Power poles and lines and telecommunication fiber have been installed. The old power poles have been removed or replaced with new poles. The Department of Transportation and Mobility has selected Granite Construction Company as the contractor for this project. Roadway construction is expected to begin on Monday, May 20, 2024.

The Regional Transportation Authority’s (RTA) board approved the Intergovernmental Agreement (IGA) to provide funding for the upcoming construction phase. The IGA will be presented to the Tucson Mayor and Council on January 11, 2023.

 

Previous Phase 3 & 4 Information (Sparkman to Swan)

 

Current Phase 5 & 6 Information (Campbell/Country Club)

 

Background

The Regional Transportation Authority, a political subdivision of the state and independently governed, has invested more than $1.4 billion in transportation projects and services to improve mobility, safety, economic vitality and quality of life in the region. The RTA collects a half-cent excise (sales) tax from its special taxing district within Pima County to fund its 20-year regional transportation plan. The plan and tax were approved by voters in May 2006. The Grant Road Improvement project is part of the RTA plan and is managed by City of Tucson, Department of Transportation and Mobility. For more information, visit RTAmobility.com.

 

 

Phase 1
Oracle
Phase 2
Stone/Park
Phase 5&6
Campbell/Country Club
Phase 3&4
Sparkman/Swan
  • Substantially Complete
  • Construction cost estimate $11 million
  • Complete construction cost $7 million
more ›
  • Utilities Clearance: Estimated Completion in December 2016
  • Construction Period: 2017-2018
  • Construction Contract Amount, Estimated: $14.5 Million
more ›
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2021-2025
  • Estimated Construction Cost: $42 Million
  • Phases 3 & 4 to be Built Concurrently
more ›
  • Utilities Clearance: Approx. 12 months
  • Construction to Start: 2026
  • Estimated Construction Cost: $50 million
  • Phases 5 & 6 to be Built Concurrently
more ›