Grant Road Improvement Plan

  •  
    Grant Road Improvement Plan

    Welcome to the new Grant Road Website. We are currently updating our website. If you have any questions or need additional information, please contact information@grantroad.info or 624-4727

  •  
    Grant Road Improvement Plan

    New and wider sidewalks, more signalized crosswalks, improved bicycle lanes, and enhanced landscaping will greatly improve both the pedestrian and bicyclist use and the appearance of Grant Road.

  •  
    Grant Road Improvement Plan

    When complete, Grant Road will greatly improve our region's east-west mobility by adding a new travel lane in each direction.

  •  
    Grant Road Improvement Plan

    Please join our Open House
    on Wednesday, Nov 19th
    5:30 – 7:00 pm

    Brief presentation at 5:45 pm
    Tucson Association of Realtors
    2445 N. Tucson Blvd.

City of Tucson's Grant Road Improvement Plan

Voters approved the Grant Road Improvement Project and its half cent sales tax funding in May 2006 as part of the $2.1 billion dollar Regional Transportation Authority (RTA) plan. The improvements to the five-mile section of Grant Road between Oracle Road and Swan Road include widening to six lanes with bike lanes, and streetscape and pedestrian improvements to create a state-of-the-art, multi-modal transportation corridor.

Phase 1
Oracle
Phase 2
Stone/Park
Phase 5&6
Campbell/Country Club
Phase 3&4
Alvernon/Swan
  • Substantially Complete
more ›
  • RTA Funding Period 2 (2012-2016)
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2015-2017
  • Estimated Construction Cost: $19 million
more ›
  • RTA Funding Period 3 ( 2017-2021)
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2017-2019
  • Estimated Construction Cost: $31 Million
  • Phases 3 & 4 to be built concurrently
more ›
  • RTA Funding Period 3/4 (2021-2026)
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2021-2023
  • Estimated Construction Cost: $33 Million
  • Phases 5 & 6 to be built concurrently
more ›